HS2 Works Notification: Road closure and traffic management, Rocky Lane and the A413

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-26-08/06/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Contractor
EKFB JV
Type of works
Cable works, Enabling works, Installation Works, Lane closure, Road closure, Traffic management, Utility works / surveys
Estimated Start Date
23/05/2022
Estimated End Date
18/06/2022

What we are doing

We are installing electricity cables along Rocky Lane and the A413, London Road; these cables will provide power to our conveyor.

  • Rocky Lane will be fully closed, 24 hours a day, from Monday 23 May 2022 for approximately three weeks, with a signed diversion in place. To reduce disruption as much as possible, the Lane will be reopened for Saturday 11 June and Sunday 12 June 2022.
  • The A413 London Road will have temporary traffic management, in the form of a lane closure with two-way traffic lights, from Monday 30 May 2022 for approximately two weeks. To reduce disruption as much as possible, the
    traffic management will be removed for Saturday 11 June and Sunday 12 June 2022.

We will maintain access for local residents and do not anticipate any disruption to local utility services.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]