HS2 Works Notification: Road closure, Stratton Audley Road, Chetwode
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-49-10/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Chetwode
- Contractor
- EKFB JV
- Type of works
- Early construction works, Road closure, Traffic management
- Estimated Start Date
- 25/10/2021
- Estimated End Date
- 08/11/2021
What we are doing
As part of our continued preparatory works for our internal haul road we will close Stratton Audley Road, by School End, for approximately one week.
To build the haul road we will create a strengthened surface using concrete to ensure that we protect the road and any utilities underneath it for the duration of our works. Once the crossing point is created, Stratton Audley Road will then be reopened, with gates in place to keep local traffic separated from construction traffic.
Stratton Audley Road will be fully closed, 24 hours a day, Monday 1 November to Monday 8 November, with a diversion route in place. We will work to reopen the roads as soon as possible, to reduce disruption.