HS2 Works Notification: Road closure, Chetwode

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-34-07/04/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Barton Hartshorn, Chetwode
Contractor
EKFB JV
Type of works
Road closure, Survey
Estimated Start Date
21/07/2022
Estimated End Date
21/07/2022

What we are doing

In July, we will be carrying out topographical surveys on Barton Hartshorn Road, also known as Stratton Audley Road, Chetwode.

Topographical surveys will help us to finalise the design of the new railway and road alignments and where possible allow us to reinstate features after construction.

These surveys are part of our preparatory works for the School End bridge. Once completed, this bridge will carry traffic over the HS2 rail line.

In order to carry out these surveys safely and effectively, we will need to put in place a daytime road closure with signed diversion. This is required because our staff will be working directly on the carriageway.

Barton Hartshorn Road will be fully closed, from 8.00am to 6.00pm on Thursday 21 July 2022, with a local diversion route in place.

We will work to reopen the roads as soon as possible, to reduce disruption.