HS2 Works Notification: Road closure, Culworth Road, Chipping Warden
Work item: HS2-EW-EK-Ph1-Ar-Ce-C3-Traf-44-12/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Chipping Warden, Edgcote
- Contractor
- EKFB JV
- Type of works
- Early construction works, Road closure, Utility works / surveys
- Estimated Start Date
- 17/01/2022
- Estimated End Date
- 01/02/2022
What we are doing
As part of our continued preparatory works, we will be closing a section of Culworth Road for approximately two weeks in January.
We will be carrying out Ground Investigation (GI) works along Culworth Road. Our GI works will involve surveys and trial holes. These surveys and trial holes will allow for accurate detection and identification of existing services and utilities.
As the project progresses, it is also necessary to remove vegetation to enable future works to continue and to allow access to areas of the site, enabling us to complete our works along Culworth Road.
A section of Culworth Road will be closed from, 8.00am to 6.00pm, Monday 17 January and remain in place for approximately two weeks.
To reduce disruption as much as possible, we do not intend to close this road over the weekend.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]