HS2 Works Notification: Road closure Fiddlers Field/Snakes Lane, Quainton (update)

Work item: HS2-MW-EK-Ph1-Ar-So-S1-Prog-works-1-31/03/2023,

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Contractor
EKFB JV
Type of works
Road closure, Vegetation clearance
Estimated Start Date
24/06/2023
Estimated End Date
25/06/2023

What we are doing

In June 2023, we will be temporarily closing Fiddlers Field/Snakes Lane for 48 hours from Saturday 24 to Sunday 25 June 2023 while we make preparations to build its connection to the Station Road realignment. These works will include the careful removal of some vegetation around where the link between the two roads will be built.

Prior to any vegetation removal, an ecologist will complete a detailed survey of the area to be cleared. Any protected species found to be present will be recorded and the vegetation will be left undisturbed with the appropriate buffer zone established. Vegetation clearance will only commence once further surveys and mitigation can be established to confirm that the protected species are no longer present.

Fiddlers Field/Snakes Lane will be closed between the junctions with Lee Road and Station Road with a signed diversion route. This closure is necessary for safety reasons as our teams will be working on and around the carriageway.

Access for residents, emergency services and farm traffic will be maintained.

These dates may be subject to change due to circumstances outside of our control, such as weather. Please refer to the HS2 website regularly to check for any changes or updates.