HS2 Works Notification: Road closure programme update, Quainton
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-21-11/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- BT Openreach
- Type of works
- Road closure, Utility works / surveys
- Estimated Start Date
- 21/11/2022
- Estimated End Date
- 16/11/2022
What we are doing
A section of Quainton Road will be closed 24-hours a day from Monday 21 November to Friday 16 December 2022., we will be carrying out some BT utility diversion works across Quainton Road. To help reduce our impact on the local area, Thames Water will be using the same closure to carry out the diversion of a water main.
As our teams will be working in an open trench across Quainton Road, this section of road will be closed 24-hours a day for approximately four weeks.
These dates may change due to conditions outside of our control. Please refer to the HS2 website regularly to check for any changes and updates.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]