HS2 Works Notification: Road closure, Station Road, Quainton
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-10-01/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- EKFB JV
- Type of works
- Enabling works, Ground investigations, Road closure
- Estimated Start Date
- 21/03/2022
- Estimated End Date
- 11/04/2022
What we are doing
We will be closing a section of Station Road for approximately one week, as part of our continued preparatory works,
We will be carrying out Ground Investigation (GI) works along Station Road between the entrance to Buckinghamshire Railway Centre and the crossroads. Our GI works will involve surveys and trial holes which will allow for the accurate detection and identification of existing services and utilities.
Station Road will be fully closed, 24 hours a day, from Monday 21 March 2022 to Saturday 26 March 2022, with a diversion in place. We will work to open the roads to reduce disruption as soon as possible.
Some additional weekend work may also take place.
Due to circumstances outside of our control, such as weather, these dates may be subject to change.