HS2 Works Notification: Road closure, Steeple Claydon Road crossing point
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-45-02/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Steeple Claydon, Twyford
- Contractor
- EKFB JV
- Type of works
- Early construction works, Road closure, Traffic management
- Estimated Start Date
- 29/11/2021
- Estimated End Date
- 13/12/2021
What we are doing
As part of our continued preparatory works for our internal haul and access roads we will need to close a section of Steeple Claydon Road for approximately one week to construct a crossing point.
As the preparatory works will require large plant and machinery, we are required to fully close this section of road, 24 hours per day, until they are complete. This is for the safety of road users and our staff.
A section of Steeple Claydon Road will be closed, 24 hours per day, from Monday 29 November to Monday 6 December, with a diversion in place and we will work to reopen the road as soon as possible.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]