HS2 Works Notification: Road closure, Wardington Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-47-12/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Chipping Warden, Edgcote, Wardington
Contractor
EKFB JV
Type of works
Early construction works, Road closure, Utility works / surveys
Estimated Start Date
10/01/2022
Estimated End Date
19/01/2022

What we are doing

As part of our continued preparatory works for our internal haul and access roads, in January 2022 we will be closing a section of Wardington Road, near Welsh Road.

It is necessary to carry out essential Ground Investigation surveys (GI) and trial holes, to ensure that where our access road crosses the highway, we protect the road and any utilities underneath.

We need to close the road for the safety of road users and our staff, who will be working directly in the centre of the highway.

A section of Wardington Road will be closed from, 8.00am to 6.00pm, Monday 10 January, for approximately one week.

The duration of the road closure will depend on the initial surveys and we will re-open the road as soon as possible.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]