View route map
HS2 Works Notification: Road closures programme, Quainton update
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-2-09/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- EKFB JV
- Type of works
- Road closure, Road repairs, Utility works / surveys
- Estimated Start Date
- 31/10/2022
- Estimated End Date
- 14/11/2022
What we are doing
In late October, we will be carrying out some urgent road repairs, utility diversion works as well as junction improvements in Quainton. Once our road repairs are complete we will then begin utility diversion works along a section of Quainton Road. As we will be working in close proximity to the highway, this section of Quainton Road will be closed during the day for approximately one week.
- A section of Station Road South will be fully closed overnight from the crossroads to our site entrance between 8pm to 6am, Thursday 3 November to Saturday 5 November 2022.
- A section of Quainton Road will be closed during the day between 8.00am and 6.00pm from Monday 7 November to Monday 14 November 2022.
- The crossroads of Station Road and Quainton Road will be shut for approximately 3 hours between 8pm and 6am for one night only, week commencing Monday 7 November 2022.
These dates may change due to conditions outside of our control. Please refer to the HS2 website regularly to check for any changes and updates.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]