HS2 Works Notification: School Hill Bridge, Calvert

Work item: HS2-EW-EK-Ph1-Ar-Ce-C2-OTH-50-28/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Calvert
Contractor
EKFB JV
Type of works
Demolition works, Early construction works, Traffic management, Utility works / surveys
Estimated Start Date
17/08/2022
Estimated End Date
31/12/2022

What we are doing

From the middle of August 2022, we will begin our early works for the construction of School Hill Bridge.

These works will involve the demolition of properties on School Hill/top of Werner Terrace:

• Station House
• 12a & 12b Brackley Lane

To reduce our impact on the local road network, the main access to these sites will be through the rear of the properties. All material will be transported to our sites via temporary ramps over the old railway lines. Dilapidation surveys have been carried out and some of the materials will be reused and/or recycled. Temporary screening will be installed around the structures to help mitigate any noise or dust that will be generated by our works.

Once these works are completed, we will then begin works to disconnect any existing utilities that are located along the current bridge. To carry out these utility works, some temporary traffic management may be needed. We will continue to update communities once further details have been confirmed.

These works will take place during our normal working hours, Monday-Friday, 8.00am – 6.00pm.

The main construction works for the new School Hill Bridge are expected to commence in early 2023.