HS2 Works Notification: Surveys and road repairs, A418, Oxford Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Prog-works-33-18/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A418, Aylesbury
- Contractor
- EKFB JV
- Type of works
- Lane closure, Road repairs, Utility works / surveys
- Estimated Start Date
- 26/03/2022
- Estimated End Date
- 15/04/2022
What we are doing
In late March, we will be carrying out some road repairs along the A418 Oxford Road. These works will require temporary traffic management in the form of a lane closure with two-way traffic lights.
We will also be carrying out drainage works on the A418 Oxford Road. A camera will be used to investigate and survey the condition of the drainage system.
The A418 Oxford Road will have temporary traffic management in the form of a lane closure with two-way traffic lights on Saturday 26 March from 8.00am to 1.00pm.
There will also be temporary traffic management on the A418 Oxford Road overnight from 10.00pm to 5.00am, Monday 28 March to Friday 1
April 2022.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]