HS2 Works Notification: Temporary closure, Kineton Road, Southam
Work item: HS2-MW-EK-Ph1-Ar-Ce-C3-Traf-3-16/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Southam
- Contractor
- EKFB JV
- Type of works
- Early construction works, Lane closure, Road closure, Traffic management
- Estimated Start Date
- 05/01/2022
- Estimated End Date
- 31/01/2022
What we are doing
As part of the construction of our internal haul and access roads, we need to create a crossing point on Kineton Road in January 2022.
These works will involve creating a strengthened surface using concrete to ensure that we protect the road and any utilities underneath it for the duration of our works.
As the preparatory works will require large plant and machinery, and time for concrete to set, we are required to fully close a section of Kineton Road, 24 hours per day. This is for the safety of road users and our staff, who will be working directly in the centre of the highway.
We will have temporary traffic management, in the form of two-way traffic lights, on the Kineton Road for approximately two weeks, from Wednesday 5 January to Sunday 16 January 2022. This will be followed by the full closure of a small section of the Kineton Road, 24 hours a day, from Wednesday 19 January to Monday 31 January 2022 with a diversion in place.
We will work to open the roads to reduce disruption as soon as possible.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]