HS2 Works Notification: Temporary road closure, Mixbury
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-1-27/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Oxfordshire
- Location
- Mixbury
- Contractor
- EKFB JV
- Type of works
- Early construction works, Road closure
- Estimated Start Date
- 14/09/2021
- Estimated End Date
- 28/09/2021
What we are doing
As part of our continued preparatory works for our internal haul and access roads, we will need to close Featherbed Lane, also known as Fulwell Lane, for approximately 2 weeks in September to construct a crossing point.
Under this closure, we will create a strengthened surface using concrete to ensure that we protect the road and any utilities underneath it for the duration of our works. This crossing point will then replace the temporary crossing constructed in June 2021.
The closure will be in place 24 hours a day, from Tuesday 14 September to Tuesday 28 September, with a diversion in place. We will work to open the road as soon as possible to reduce disruption.
Download information relating to these works