HS2 Works Notification: Temporary road closure, Mixbury

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-1-27/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Oxfordshire
Location
Mixbury
Contractor
EKFB JV
Type of works
Early construction works, Road closure
Estimated Start Date
14/09/2021
Estimated End Date
28/09/2021

What we are doing

As part of our continued preparatory works for our internal haul and access roads, we will need to close Featherbed Lane, also known as Fulwell Lane, for approximately 2 weeks in September to construct a crossing point.

Under this closure, we will create a strengthened surface using concrete to ensure that we protect the road and any utilities underneath it for the duration of our works. This crossing point will then replace the temporary crossing constructed in June 2021.

The closure will be in place 24 hours a day, from Tuesday 14 September to Tuesday 28 September, with a diversion in place. We will work to open the road as soon as possible to reduce disruption.