HS2 Works Notification: Temporary road closures update, Mixbury
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-11-10/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Mixbury
- Type of works
- Construction, Road closure
- Estimated Start Date
- 24/04/2023
- Estimated End Date
- 05/05/2023
What we are doing
As part of our continued works for the new permanent realignment of Featherbed Lane and the Featherbed Lane Overbridge, we will be completing the tie ins for the temporary diversion of Featherbed Lane, also known as Lane through Fulwell.
Our works will include road surfacing, white lining and the installation of road signage. Once our works are completed, a road safety audit will be carried out before the temporary diversion is open for public use.
Due to the nature of the works, there will be open trenches across the highway and for reasons of safety we will require full road closures. There will also be noise from large plant and machinery.
After the tie ins are complete, there will also be temporary traffic lights in this location while we build the Featherbed Lane Overbridge.
The junction of Church Lane and Featherbed Lane will be fully closed from Monday 24 April to Friday 5 May 2023, access will be maintained for local businesses.
There will also be traffic management in the form of temporary traffic lights in this location from the end of April and into the summer 2023.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]