HS2 Works Notification: Traffic management, A361, Chipping Warden

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-22-12/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Chipping Warden
Contractor
EKFB JV
Type of works
Traffic management, Trial Pits, Utility works / surveys
Estimated Start Date
23/01/2023
Estimated End Date
06/02/2023

What we are doing

Prior to the next phase of construction on the Chipping Warden Green Tunnel, we need to accurately identify and inspect the existing utilities that are located under the A361 near to our compound entrance.  

A section of the A361 will have temporary traffic management in the form of traffic lights, on weekdays from Monday 23 January to Saturday 4 February 2023. This will take place during the daytime, from 8am to 6pm Mondays to Fridays, and 8am-1pm on Saturdays 

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]