HS2 Works Notification: Traffic management update, A41
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-7-18/05/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A41, Buckinghamshire, Fleet Marston
- Contractor
- EKFB JV
- Type of works
- Ground investigations, Utility works / surveys
- Estimated Start Date
- 14/11/2022
- Estimated End Date
- 18/11/2022
What we are doing
In early November, we will be carrying out Ground Investigation (GI) works along the A41. These works will take just over a week to complete. Our GI works will involve surveys and trial holes. These activities will allow us to accurately identify the location of utilities that will need to be diverted while we build HS2.
As we will be conducting these surveys and trial holes very close to the local highway, we will need to introduce traffic management in the form of a lane closure with traffic lights.
A section of A41 Bicester Road will have traffic management from Monday 14 November to Friday 18 November 2022, from 9.00am to 3.00pm.