HS2 Works Notification: Traffic management update, A41

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-7-18/05/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A41, Buckinghamshire, Fleet Marston
Contractor
EKFB JV
Type of works
Ground investigations, Utility works / surveys
Estimated Start Date
14/11/2022
Estimated End Date
18/11/2022

What we are doing

In early November, we will be carrying out Ground Investigation (GI) works along the A41. These works will take just over a week to complete. Our GI works will involve surveys and trial holes. These activities will allow us to accurately identify the location of utilities that will need to be diverted while we build HS2.

As we will be conducting these surveys and trial holes very close to the local highway, we will need to introduce traffic management in the form of a lane closure with traffic lights.

A section of A41 Bicester Road will have traffic management from Monday 14 November to Friday 18 November 2022, from 9.00am to 3.00pm.