HS2 Works Notification: Traffic management update, Blackgrove Road
Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-7-30/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Fleet Marston
- Contractor
- BT Openreach, EKFB JV, Thames Water
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 27/02/2023
- Estimated End Date
- 22/09/2023
What we are doing
We will be carrying out BT and Thames Water utility diversion works along Blackgrove Road. The Utility teams will be working on diverting the existing connections and farm access works. We are required to conduct this work ahead of the A41 realignment works due to commence in the new year.
As we are working around the carriageway, we will need to implement traffic lights for road users.
In addition to the utility works, we will also be conducting some localised vegetation clearance which will allow us to clear the area needed construct the new A41 alignment.
Traffic management will be on Blackgrove Road from Monday 27 February 2023 to Summer 2023 from 9am to 5pm. During these times, a section of Blackgrove Road near our works area will have temporary traffic lights in use.
Unfortunately, this work has taken longer than anticipated due to conditions outside of our control but we will endeavour to complete the works within the specified times.
Please refer to the HS2 website to check for any changes and updates.