HS2 Works Notification: Traffic management, Gawcott Road/Perry Hill, Calvert
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-01-19/04/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Calvert
- Contractor
- EKFB JV
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 11/05/2023
- Estimated End Date
- 11/06/2023
What we are doing
In mid-May 2023, we will be carrying out some work on electric cable installation on Gawcott Road. These works will be completed under 4 way lights.
Following on from these works we will be working on a gas pipe underneath Gawcott Road/Perry Hill which must be disconnected and decommissioned before the bridge can be safely demolished later in the year.
To carry out these works safely and effectively, two sections of Gawcott Road/Perry Hill will require traffic management. These works are an important step towards the re-alignment of Gawcott Road/Perry Hill over the new bridge, currently under construction.
The first section of Gawcott Road/Perry Hill will be under traffic management to complete works on electrical cable installation will be Thursday 11 and Friday 12 May.
Following on from these works, a further two sections of Gawcott Road/Perry Hill will be under traffic management from Monday 15 May and Sunday 11 June 2023 near the entrance of the Great Moor Sailing Club and near the entrance of the EKFB West Street Compound to disconnect and decommission the gas pipe.
These dates may be subject to change due to circumstances outside of our control, such as weather
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]