HS2 Works Notification: Traffic management on Forest Close and Dobbins Lane, Wendover
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-9-18/04/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Wendover
- Contractor
- EKFB JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 30/05/2023
- Estimated End Date
- 07/06/2023
What we are doing
From late May into June, we will need to implement traffic management at the junction between Forest Close and Dobbins Lane to continue the water main maintenance works.
To reduce the number of deliveries to our sites and to maintain a sustainable source of water for our works, we will be establishing a connection to a water main to supply our Wendover Green Tunnel
compound.
To ensure this diversion will not affect the water pressure of Wendover town residences, our subcontractor, Clancy, will be carrying out maintenance works in the area.
As the water main access points are in specific locations on Forest Close and Dobbins Lane, we will need to introduce temporary traffic lights at this junction location to ensure both road users and our workforce are kept safe throughout the works.
We will also need to close a small section of Dobbins Lane at the junction with Wendover High Street for three days to complete these works, a signposted diversion route will be in place.
Resident and business access will be maintained throughout.
Works take place:
- Forest Close/Dobbins Lane junction – Tuesday 30 May to Sunday 4 June
- Dobbins Lane closure at the junction with the High Street –Monday 5 June to Wednesday 7 June
These dates may be subject to change due to circumstances outside of our control but will be completed on or around the timings specified.