HS2 Works Notification: Underground utility cable works near Radstone Road

Work item: HS2-EW-UT-Ph1-Ar-Ce-N1-Prog-works-24-31/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Radstone
Contractor
Western Power Distribution
Type of works
Utility works / surveys
Estimated Start Date
31/08/2021
Estimated End Date
30/09/2021

What we are doing

Western Power Distribution will be completing the remaining works on a 33kV utility cable diversion in the Radstone area. The work will involve removing the redundant cable and connecting the new cable to the network through a process called ‘jointing’. The work will be taking place on land to the south of Radstone village, off Radstone Road.