HS2 Works Notification: Update ground investigations in Alperton Lane
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-05/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Westgate
- Worksite Name
- Westgate
- Contractor
- SCS JV
- Type of works
- Ground investigations
- Estimated Start Date
- 25/10/2021
- Estimated End Date
- 30/11/2021
What we are doing
Ground investigation works from 13 September
We recently wrote to you in early September about ground investigation works in the Alperton Lane area from 27 September until 30 October. These works have now been rescheduled and will take place from 25
October until 30 November between 8am to 6pm on Mondays to Fridays.
The ground investigation works will involve drilling two holes into the ground and installation of monitoring equipment below ground on the main sewage pipes. We are installing the monitoring equipment so we
can monitor the condition of the sewage pipes while we build the HS2 tunnels.
We will need to remove some low level vegetation such as shrubs and bushes within the Network Rail land. These works will take place before the ground investigation works.
You can view our previous notification about ground investigation works in the Alperton Lane area at hs2.org.uk/where/route-map/
Dates mentioned in this notification may change due to unforeseen circumstances. We will continue to provide updates about our works at HS2inyourarea.co.uk
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]