HS2 Works Notification: Utility works update, A418 Oxford Road and Stoke Mandeville

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-23-22/10/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A418, Stoke Mandeville
Worksite Name
A418 Aylesbury
Contractor
Thames Water, UK Power Networks
Type of works
Traffic management, Utility works / surveys
Estimated Start Date
31/10/2022
Estimated End Date
12/11/2022

What we are doing

As part of continued preparatory works, there will be utility works happening along the A418 and Stoke Mandeville area.

Thames Water will be conducting a water connection within the verge along the A418. In order to carry out these works safely, we will need to introduce temporary traffic management in the form of a lane closure with three-way traffic lights. We will work to open the lanes to reduce disruption as soon as possible.

Thames Water will also be conducting some works on the water supply in the Stoke Mandeville area. Thames Water should be contacting these residents directly. No traffic management is required for this work.

UKPN will be diverting an electricity cable adjacent to the A418. This diversion will facilitate upcoming works for the permanent realignment of the A418.

The A418 will have traffic management overnight from 8:00pm to 6.00am from Monday 31 October 2022 for approximately 5 days.

There may cause a temporary disruption to the power supply on Monday 7 November and/or Saturday 12 of November 2022 to a few properties adjacent to the A418.

We understand that we are providing short notice for these works; unfortunately, utility-related works are sometimes confirmed with short notice.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]