HS2 Works Notification: Utility works, Brackley Lane and Calvert Road, Calvert (update)
Work item: FUS_AWN_0289 HS2-EW-Fusion -Ph1-Ar-Ce-C2-UT-41-30/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Calvert
- Contractor
- Fusion JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 04/01/2022
- Estimated End Date
- 18/03/2022
What we are doing
We will be undertaking further trenching and connection works in Calvert Road and Brackley Lane which will require traffic management. These works will take place in early 2022
You will be contacted directly by your utility supplier if there are any outages to your supply. No outages are anticipated for the works in January and February 2022.
We will need to install 3-way lights on the junction of Brackley Lane and Werner Terrace, these lights will be installed in Spring 2022 to enable BT, WPD and Anglian Water to connect their existing services
to the newly diverted cables and pipes. We will keep you updated ahead of these works starting.
Brackley Lane
Ongoing utility trenching and ducting works under 3 way traffic light control at the junction of Cotswolds Way and Brackley Lane – 4 January to 4 February 2022. (Subject to consents)
Following on from the trenching works, Anglian Water will undertake their utility connections work. For this work, we will need to install 3-way lights on Brackley Lane at the junction with Cotswolds Way on: 7 February 2022 until 18 February 2022, the lights will be operational 24/7. (Subject to consents).
Calvert Road – Overnight Road closure 8pm – 5am
To enable Anglian Water and BT to make their utility connections overnight road closures are required. The work will take place each night from 17 January until 4 February 2022 where Calvert Road will be closed overnight between 8pm and 5am (subject to consents). Depending on progress of works, the overnight closure may continue over the weekends, however we will be working hard to minimise disruption. Through access to emergency services will be permitted during this road closure. The diversion route will be a repeat of the earlier closure route.
Throughout both stages of works, there will be restricted residential parking on the highway