Skip to main page content
View route map

HS2 Works Notification: Utility works update, A418 Oxford Road

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-23-22/10/2022

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A418
Worksite Name
A418 Aylesbury
Contractor
BT Openreach, EKFB JV, Thames Water, UK Power Networks
Type of works
Lane closure, Utility works / surveys
Estimated Start Date
26/11/2022
Estimated End Date
28/11/2022

What we are doing

Thames Water will be creating a water connection within the verge along the A418. In order to carry out these works safely, we will need to introduce temporary traffic management in the form of a lane closure with three-way traffic lights. We will work to open the lanes to reduce disruption as soon as possible. The A418 will have traffic management during the day and overnight from 7am to Saturday 26 November 2022 to 6am Monday 28 November.

UKPN will be diverting an electricity cable adjacent to the A418. This diversion will facilitate upcoming works for the permanent realignment of the A418.