HS2 Works Notification: Welsh Road fencing works, Aston Le Walls
Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C3-Eco-39-08/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Aston Le Walls, Chipping Warden
- Contractor
- Fusion JV
- Type of works
- Fencing, Traffic management
- Estimated Start Date
- 17/01/2022
- Estimated End Date
- 25/02/2022
What we are doing
Further to our recent works in the area, we will be installing 1300 meters of new wooden post and rail fencing (this will include stock proof netting).
To minimise disruption, we plan to install the fencing from inside the field, however, there may be occasions when this is not possible, and we may require the use of local traffic management.
Works are planned to take place from 8 February 2022 for two weeks.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]