HS2 Works Notification: Works and traffic lights on Banbury Road, Wormleighton
Work item: HS2-EW-Fusion -Ph1-Ar-Ce-C3-Traf-1-06/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Wormleighton
- Contractor
- Fusion JV
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 10/01/2022
- Estimated End Date
- 28/02/2022
What we are doing
Further to our last notification regarding the flooding on Banbury Road near to the junction of Leisure Drive, we have identified a blocked and potentially damaged drainage pipe crossing underneath Banbury Road. We need to undertake further investigatory work to assess the issue and to plan any drainage improvement works that may be required.
We are currently using a road sweeper to remove the excess water as the flooding returns due to the runoff from adjacent fields.
To ensure a safe working area and passage around the flooded area, we will change the traffic management to three-way traffic lights on Banbury Road and Leisure Drive which will be in place 24/7 until the works are completed.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]