View route map
HS2 Works Notifications: Road closures of A413 London Road, Wendover in June and July
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-03-01/06/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A413
- Contractor
- EKFB JV
- Type of works
- Ground investigations, Overnight road closure, Utility works / surveys
- Estimated Start Date
- 19/06/2023
- Estimated End Date
- 03/07/2023
What we are doing
We have some upcoming works along the A413 London Road that support the construction of the A413 re-alignment and the Small Dean viaduct.
We have three phases of construction coming up that will have short duration impacts on the road from June into July;
- Overnight closures for ground investigations
- A weekend closure for utility diversions
- Traffic lights for a lane closure to continue utility diversions
Works take place:
- Monday 19 June to Friday 24 June overnight road closures 8.30pm to 5.30am
- Friday 30 June to Monday 3 July weekend closure 8.30pm on Friday night to 5.30am on Monday morning
- Friday 7 July to Monday 10 July traffic lights and lane closure 8.30 pm on Friday night to 5.30am on Monday morning
To minimise disruption, we will provide a signposted diversion route and have chosen to work outside of peak traffic hours.
These dates may be subject to change due to circumstances outside of our control.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]