HS2 Works Notifications: Road closures of A413 London Road, Wendover in June and July

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-03-01/06/2023

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Contractor
EKFB JV
Type of works
Ground investigations, Overnight road closure, Utility works / surveys
Estimated Start Date
19/06/2023
Estimated End Date
03/07/2023

What we are doing

We have some upcoming works along the A413 London Road that support the construction of the A413 re-alignment and the Small Dean viaduct.

We have three phases of construction coming up that will have short duration impacts on the road from June into July;

  • Overnight closures for ground investigations
  • A weekend closure for utility diversions
  • Traffic lights for a lane closure to continue utility diversions

Works take place:

  • Monday 19 June to Friday 24 June overnight road closures 8.30pm to 5.30am
  • Friday 30 June to Monday 3 July weekend closure 8.30pm on Friday night to 5.30am on Monday morning
  • Friday 7 July to Monday 10 July traffic lights and lane closure 8.30 pm on Friday night to 5.30am on Monday morning

To minimise disruption, we will provide a signposted diversion route and have chosen to work outside of peak traffic hours.

These dates may be subject to change due to circumstances outside of our control.