Work item: HS2-OOC - SCP-25-1384

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Construction, Crane installation, Large load delivery/collections, Worksite / compound set-up
Estimated Start Date
26/09/2025
Estimated End Date
29/02/2028

What we are doing

This is an update of works taking place within the Old Oak Common Station site from September 2025 to February 2028.

This will cover information about:

  • Additional site office – October 2025 to mid February 2026
  • South portal building construction – August 2025 to February 2028
  • Substation construction update – June 2025 to June 2026
  • Tower crane installation – 27 October for approximately 2 weeks. We have contingency dates of Sunday 26 – Monday 27 October if works are delayed due to bad weather

All construction works: Monday to Friday 8am – 6pm and Saturdays 8am – 1pm.