Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Construction, Crane installation, Large load delivery/collections, Worksite / compound set-up
- Estimated Start Date
- 26/09/2025
- Estimated End Date
- 29/02/2028
What we are doing
This is an update of works taking place within the Old Oak Common Station site from September 2025 to February 2028.
This will cover information about:
- Additional site office – October 2025 to mid February 2026
- South portal building construction – August 2025 to February 2028
- Substation construction update – June 2025 to June 2026
- Tower crane installation – 27 October for approximately 2 weeks. We have contingency dates of Sunday 26 – Monday 27 October if works are delayed due to bad weather
All construction works: Monday to Friday 8am – 6pm and Saturdays 8am – 1pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]