Installation of pedestrian crossing beacons on Channel Gate Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-CR-1-23/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Traffic management, Utility works / surveys
- Estimated Start Date
- 08/12/2021
- Estimated End Date
- 22/12/2021
What we are doing
Installation of pedestrian crossing beacons
We will be installing four crossing beacons on the pedestrian crossing on Channel Gate Road. The beacons will improve the visibility of the crossing to both pedestrians and approaching vehicles.
These works will be carried out from the 8 December to 22 December 2021 between the hours of 8am to 6pm Monday to Friday and 8am to 1pm on Saturday if required.
What to expect
During these works we will need to create foundations for the beacons. This will be done by cutting and breaking the concrete at four points on the crossing using power tools. The remaining excavation will be completed via hand tools. Once the excavation has been completed we will install the light beacons and reinstall the foundations around them.
During these works where possible, acoustics barriers will be in place to minimise the level of noise to neighbouring residents. We will also continue to monitor our working methods to ensure that any disruption to local residents is reduced as much as possible.
A map showing the approximate location of the works is included on the following page.
The beacons will be similar to the ones on the pedestrian crossing on Old Oak Lane nearby The Fishermans Arms.
Dates mentioned in this notification may change due to unforeseen circumstances. We will continue to provide updates about our works at HS2.org.uk