Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Harvil Road
- Worksite Name
- Harvil Road
- Contractor
- SCS JV
- Type of works
- Sheet piling
- Estimated Start Date
- 14/07/2025
- Estimated End Date
- 20/07/2025
What we are doing
From 14 July to 20 September 2025, we will carry out sheet piling works at our site on Harvil Road.
The piles will be installed north of the Chiltern rail line and east of the new Harvil Road bridge, within our Copthall Tunnel site.
These works are required to stabilise the ground while we build the permanent rail siding, which is part of the Copthall Tunnel design.