Installing monitoring equipment in Regents Park Estate – Augustus House
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-30/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Euston Approaches
- Contractor
- SCS JV
- Type of works
- Monitoring equipment
- Estimated Start Date
- 09/01/2023
- Estimated End Date
- 20/01/2023
What we are doing
We need to install monitoring equipment on the following buildings in the Regents Park Estate to survey ground movement: Cartmel, Harrington House, Langdale, Augustus House and Ambleside.
The residents of those building were previously notified that this was planned for 5 to 16 December but has now been rescheduled for 9 to 20 January 2023.
A small team of two or three operatives will abseil from the roof and attach small prisms to the side of the building with a small hand drill. We don’t expect these works to be noisy or disruptive.
We will use the communal parts of the building to access the roof but will not require access to your private flat. Our team will all wear HS2 identity cards. We will complete installation in about two to three days per building.
Once installed, our survey team will visit to take regular readings and carry out any required maintenance on the instruments. The team will use a tripod to survey the prisms from the street. This equipment collects monitoring data but does not take images, so your privacy is protected.
For further details please see the notice below.