Road reinstatement: Kilburn High Road, Oxford Road and Greville Road

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-11/02/2025

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Camden, London
Location
Kilburn
Contractor
SCS JV
Type of works
Road reinstatement, Utility works / surveys
Estimated Start Date
03/03/2025
Estimated End Date
17/03/2025

What we are doing

From 3 to 17 March 2025 we will be carrying out road reinstatement works on Kilburn High Road, Oxford Road and Greville Road.

We will remove and relay cracked tarmac, repaint the road markings, relay some cobbles and fill in gaps between paving.

These works will be done in three phases as shown on the table below.

DateWork location
3 to 5 MarchA northbound lane closure on Kilburn High Road.

Partial road closures on Oxford Road and Greville Road.

5 to 9 MarchA southbound lane closure on Kilburn High Road.

Partial road closures on Oxford Road and Greville Road.

10 to 17 MarchPartial Road closures on Oxford Road and Greville Road.

There will be clearly marked traffic diversions in place. Traffic on Kilburn High Road will be managed with temporary traffic lights.

While there are works on Kilburn High Road, bus stop X, outside Anytime Fitness, and bus stop W, outside Starbucks, will be suspended. Please plan ahead of any travel using buses in this area during the works. You can find the latest bus status update via www.tfl.gov.uk/plan-a-journey.

For further details of above please see the notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]