View route map
Lane and footpath closure on Victoria Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2 -Prog Works-1-04/09/24
Work Item Summary
- Project Phase
- Phase 1
- Region
- London, Old Oak and North Acton
- Location
- North Acton
- Worksite Name
- Victoria Road
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 23/09/2024
- Estimated End Date
- 04/10/2024
What we are doing
Between 23 September and 4 October 2024, we will close a section of lane and footpath on Victoria Road to carry out construction works.
The closures are needed to safely accommodate substation works, which include excavations, hoarding removal, concreting and fence installation. The works will be carried out in two phases.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]