Main site activities at Mandeville Road

Work item: HS2-MW-SCS-Ph1-Ar-So-S1-CR-9-07/12/2021

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Early construction works
Estimated Start Date
01/12/2021
Estimated End Date
31/12/2025

What we are doing

We are building two ventilation (vent) shafts and a headhouse at the Mandeville Road site in Northolt. This is one of four vent shaft and headhouse sites on the 13.5km section of the Northolt Tunnel between Old Oak Common station and the West Ruislip portal.

Each week, we’ll produce a map showing the main construction activities in the Northolt area. Please use the link below to see the latest map.