Main site activities in the Breakspear Road area
Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-29-09/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Early construction works, Earth works, Utility works / surveys
- Estimated Start Date
- 01/09/2021
- Estimated End Date
- 31/12/2025
What we are doing
The River Pinn realignment works are complete. This work took place between May and December 2024. We are constructing the abutments (structures that supports an arch or the end of a bridge) in preparation for installing the footbridge in 2025.
With tunnelling completed, we have begun to dismantle the conveyor and treatment infrastructure. We will install noise barriers west and east of Breakspear Road South, south of the Ruislip Golf Course and north of the Chiltern Line.
We produce maps showing key site activities in the Breakspear Road South area, view details via the pdf document below.
These maps will be updated on a weekly basis.