Main site activities in the Colne Valley Viaduct area
Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-27-09/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Colne Valley
- Contractor
- Align JV
- Type of works
- Earth works, Excavation works, Piling
- Estimated Start Date
- 01/09/2021
- Estimated End Date
- 31/12/2025
What we are doing
Work on the Colne Valley viaduct will complete in August 2025. Landscaping continues at the former Hillingdon Outdoor Activity Centre site, off Dews Lane and along the length of the viaduct. This will complete by the end of 2025.
We produce weekly maps showing key site activities in the Colne Valley area, for details please follow the link below.