Main site activities in the Colne Valley Viaduct area

Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-27-09/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Colne Valley
Contractor
Align JV
Type of works
Earth works, Excavation works, Piling
Estimated Start Date
01/09/2021
Estimated End Date
31/12/2025

What we are doing

Work on the Colne Valley viaduct will complete in August 2025. Landscaping continues at the former Hillingdon Outdoor Activity Centre site, off Dews Lane and along the length of the viaduct. This will complete by the end of 2025.

We produce weekly maps showing key site activities in the Colne Valley area, for details please follow the link below.