Main utility works in the South Ruislip area

Work item: TBC

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
South Ruislip
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
25/07/2022
Estimated End Date
31/12/2023

What we are doing

The new HS2 tunnels broadly follow the route of the Chiltern Mainline Railway and London Underground Central Line. This means that the new HS2 tunnel will run beneath several major roads, some of which have significant utilities embedded within them. This includes:

  • Ickenham Road
  • Blenheim Crescent
  • West End Road
  • Bridgwater Road
  • Station Approach

Two Tunnel Boring Machines (TBMs) are constructing the tunnels, and this will cause small movements in the ground, known as settlement. Extensive surveying of the area has been conducted to understand how the utilities will respond to settlement and what measures are required in advance of the tunnelling, such as monitoring, strengthing or diverting the utilities. To ensure our operatives can complete these works safely, traffic management measures such as lane closures and temporary traffic lights are required.

The main utilities’ protection and diversion programme started in January 2022 and is due to continue until December 2023.

We produce maps showing key site activities in the South Ruislip area.

These maps will be updated on a weekly basis.