Mandeville Road site 24-hour working – New start/End date including May bank holidays
Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Prog-works-20-20/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Badminton Close, Carr Road, Mandeville Road
- Worksite Name
- Mandeville Road
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 24/04/2023
- Estimated End Date
- 04/05/2024
What we are doing
We have been speaking to residents about our works at the Mandeville Road site that will need to increase to 24 hours a day, seven days a week from 24 April 2023. This will include the May bank holidays. We expect this to last until May 2024 and we will provide regular updates to residents.
We would like to apologise for an error in the last announcement which stated the end date to be December 2023.
From 24 April 2023 we will be building the shafts during days and nights by excavating and installing concrete on to the exposed face of the clay to stabilise it. We will reduce the works we carry out at night to the minimum possible and we will use acoustic barriers around the construction machinery to reduce the noise as much as possible.
We don’t expect noise levels to exceed an average of 60 decibels, measured over a one hour period, which is equivalent to the noise of a dishwasher.
Lorries may exit and enter the site on Saturday and Sunday between 8am and-6pm to remove excavated material and deliver concrete.
From 24 April to 14 May we will try to limit our 24 hour working to every other weekend.
From 15 May to 6 August we expect to be working 24 hours every weekend because the work during this time period needs to be continuous.
We would like to apologise in advance for any disruption or inconvenience the increased working hours may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We will ensure that disruption is kept to a minimum and that regular updates are provided.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]