Skip to main page content
View route map

Network Rail work at Old Oak Common station site

Work item: N/A

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Contractor
Network Rail, Network Rail (Euston)
Type of works
Demolition works
Estimated Start Date
15/05/2021
Estimated End Date
16/05/2021

What we are doing

Network Rail will remove a redundant telecom tower at the HS2 Old Oak Common station site on the evening of 15 May into the 16 May between the hours of 12am to 4am. The tower is approximately 30 years old and the system it once supported is no longer used on the rail network.

This work is by Network Rail and any contact should be made direct to them on 03457 11 41 41.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]