Work item: N/A

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Clarkson Row, Euston station
Worksite Name
Euston Station
Contractor
Network Rail
Type of works
Construction, Delivery of materials, Enabling works
Estimated Start Date
07/04/2023
Estimated End Date
11/04/2023

What we are doing

Euston Station – Easter 2023

Network Rail will carry out some work activities during a four-day closure of Euston Station from Friday 7 April to Monday 10 April.

This also will include delivery of materials and construction works on trackside level near Clarkson Row.

Please see the notification below for further details of works over Easter period.

 