Newyears Green Lane closure for conveyor removal

Work item: Newyears Green Lane closure for conveyor removal

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Newyears Green Lane
Worksite Name
Copthall
Contractor
SCS JV
Type of works
Conveyor, Road closure
Estimated Start Date
28/05/2024
Estimated End Date
01/06/2024

What we are doing

From 28 May to 1 June 2024, we will be carrying out works to remove the conveyor bridge over Newyears Green Lane.

Due to the location of these works, a road closure will be in place to ensure these activities can be carried out safely.

During these works, access will be maintained for residents, emergency services and businesses along Newyears Green Lane. A clearly signed diversion route will be in place via Moorhall Road / A412 / A40.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.