Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-20/09/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South
- Contractor
- SCS JV
- Type of works
- Construction, Road closure, Utility works / surveys
- Estimated Start Date
- 17/10/2022
- Estimated End Date
- 24/10/2022
What we are doing
What we are doing
From 17 to 24 October, we will start constructing the new bridge along Breakspear Road South, north and south of the Network Rail bridge.
For safety reasons, a road closure will be in place for the duration of these works, however we will reopen the road at the end of each shift.
We will be:
• installing seven precast concrete bridge beams which will span over and across Breakspear Road South public highway. This will allow us to start constructing the surface of the new bridge.
• carrying out drainage investigation works. We will capture 3-dimensional information on the drainage system using a CCTV camera mounted on a small robot.
During the road closure access will be maintained for residents and emergency services.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We will ensure that disruption is kept to a minimum.
The location of the closure and the diversion is shown on the next page.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]