Notice: increase in train movements from Willesden Euroterminal site

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-23/02/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Worksite Name
Old Oak Common
Contractor
SCS JV
Type of works
Removal of excavated materials by rail
Estimated Start Date
01/03/2022
Estimated End Date
31/03/2024

What we are doing

Increase in train departures from Willesden Euroterminal from March 2022
We are continuing to receive excavated materials to the Willesden Euroterminal from other HS2 sites in the Old Oak area.
From early March 2022, we are expecting to increase to up to two train movements per day from Willesden Euroterminal to continue removing the excavated materials from the local area by rail. This date may change.

The departure of trains will continue to align with the freight rail timetable, which means that train movements will continue to take place 24/7. We’ll also continue moving rail wagons and loading the exacavated materials 24/7. The number of train movements is expected to increase again later this year – we will let you know in advance of this.

Minimising disruption to you
From late 2021, greasing guns have been in operation to reduce the screeching sound of rail movements. Our team continue to monitor these to ensure they are working as they should be. We have also replaced the bucket attachment previously used to load the trains with a clam shell grab. The clam shell grab is a quieter method which helps us to minimise noise disruption to you while we are loading the train wagons.

Our team also continue to carry out regular maintenance of the railway tracks.