- Bridge works, Railway systems
- Estimated Start Date
- 15/07/2023
- Estimated End Date
- 24/07/2023
What we are doing
Since early 2022 we have been constructing Fulfen Wood Overbridge, on land next to the West Coast main line railway in Streethay. The
bridge will allow HS2 to pass under the West Coast main line. The Fulfen Wood Overbridge will be installed during a nine day closure of a section of the railway between Rugby & Stafford in July 2023. During the closure we will:
- Remove the signals, railway tracks and excavate the embankment.
- Use specialist transport vehicles to lift and install the bridge in place
- Complete works and surveys to the bridge and re-open the railway
We have been working in partnership with Network Rail to plan the temporary closure of the West Coast main line between Stafford and Rugby. The closure will commence on 15 July 2023 and we will install the bridge and re-open the railway on 24 July 2023. Over this period, we will be working 24/7.
Please visit the National Rail website if you are planning a journey over this period:
- www.nationalrail.co.uk
To find out more about these works please visit the HS2 website:
- www.hs2.org.uk/streethay
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]