Notice of 24 hour works on the Birmingham to Derby trainline, near Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-01-04/08/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Coleshill
Contractor
BBV JV
Type of works
Construction
Estimated Start Date
19/08/2023
Estimated End Date
04/09/2023

What we are doing

To continue our works for the Curdworth Box, that will carry the railway over the existing trainline from Birmingham to Derby, we will complete works to install 25 metre long prefabricated beams. The location of this work is outlined on the map on page two. To enable this work to be completed safely, blockades will be put in place throughout the works on the existing trainline from Birmingham to Derby.

We have been working with Network Rail to plan the blockades of the Birmingham to Derby line, near Coleshill. The blockades will be in place throughout three weekends including:
• Saturday 19 August until Monday 21 August
• Saturday 26 August until Monday 28 August
• Saturday 2 September until Monday 4 September
Throughout these weekends, we will complete works 24 hours a day, from 12.01am on Saturday mornings until 4.30am on Monday mornings.

Please visit the National Rail website if you are planning a journey over this period:
www.nationalrail.co.uk