Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- A4010
- Contractor
- EKFB JV
- Type of works
- Minor works
- Estimated Start Date
- 13/03/2026
- Estimated End Date
- 16/03/2026
What we are doing
Outstanding minor works to signage, verges and the footway and crossings in various areas along the new road. We’ll need to close the road, while we complete these works, to create a safe work zone.
Location
A4010 Stoke Mandeville Relief Road
Duration
3 Nights – Friday 13 March to Monday 16 March, overnight (8.30pm to 5.30am). The road will be open during the day.
What to expect
Full overnight road closure, with associated diversion route.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]