Notice of A413, Wendover bypass weekend works January 2026

Work item: HS2-EKFB-25-1516

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A413
Worksite Name
Wendover Bypass
Contractor
EKFB JV
Type of works
Drainage installation
Estimated Start Date
10/01/2026
Estimated End Date
02/02/2026

What we are doing

Location
A413 Wendover Bypass, Wendover, Buckinghamshire

Duration
10 January – 2 February 2026

What we are doing
In early 2026, we will be continuing with site access works to the Wendover green tunnel. The work will be undertaken during
weekends. This will include drainage installation and tie-ins, and preparation for the final tie-in to the highway.

What to expect
Drainage installation adjacent to the Wendover bypass, without traffic management.
• Saturday 10 – Sunday 11 January
• Saturday 17 – Sunday 18 January
Drainage, tie-ins and highways works, 24- hour lane closure:
• Friday 23 January 8:30pm – Monday 26
January 5:30am
• Friday 30 January 8:30pm – Monday 2
February 5:30am (contingency)

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.