Notice of A423 construction compound, Southam

Work item: 1MC12-EKF-SE-NTE-CS10-000001

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Southam
Contractor
EKFB JV
Type of works
Worksite / compound set-up
Estimated Start Date
01/10/2020
Estimated End Date
31/05/2021

What we are doing

We are setting up a construction compound in a location along the route of the new railway south of Southam, off the existing A423 Banbury Road. The maps included in this notification show the location and layout of the compound. The construction compound is made up of temporary offices, welfare facilities, car parking and HGV access. All of the buildings on site will be temporary. Once the railway is built the compound and associated facilities will be removed.

This activity will include:

  1. Ground Investigation and utility works
  2. Localised clearance of vegetation and fencing
  3. Forming the access from the existing road, demolition of vacant properties and set up of works compound
  4. Drainage, and creation of settlement ponds
  5. Earthworks operations including access and haul roads.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]