Notice of A452 Southbound Road Closure
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-11-03/06/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Northway Island
- Worksite Name
- A452 Chester Road
- Contractor
- BBV JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 06/03/2023
- Estimated End Date
- 01/04/2023
What we are doing
*Updated Notice*
Works extended now until 1 April 2023
We previously contacted you to advise that these night closures would finish on 18 March. These works have been delayed because of the
snow and will now finish at 6am on 1 April
BBV have been significantly reconfiguring the junction of the A446 Stonebridge Road and A452 Chester Road near Birmingham Business Park. The new bridge over the A446 that carries the southbound slip road is already open to vehicular traffic, however as we move to completion some extra work is needed to create a pedestrian footway and some new laybys. To do this safely we will need to close the road at night between 6 March and 1 April from 9pm at night until 6am the following morning. A fully signed diversion will be in place.